GAS CO. WORKING ALONG SANTA ANITA AVE.
- shotay
- Jul 23
- 1 min read

The Gas Company has pulled three permits to improve their underground service lines along Santa Anita Ave., roughly from Huntington Dr. to Alice St. (near Fire Station 105) and on Fano St. between Santa Anita Ave. and First Ave. Work is expected to take 12 weeks total and will include temporary lane closures and steel plates to cover their area when work is not happening. We are keeping an eye on things to ensure that traffic impacts are minimized and that work is completed safely.